πŸ—οΈ Capitol Hotel β†’ Holiday Inn Express & Suites

← Back to Command Center
Pre-Construction IHG
πŸ“‹ SAMPLE DASHBOARD β€” This is a mockup showing what active project tracking looks like with AI-powered operations
105
Rooms
$13.6M
Total Budget
$1.2M
IT Budget (est.)
12
Vendors Tracked
4
Months to Opening
3
Items Need Attention

πŸ“… Project Timeline

Property Acquired
Aug 2025
DVR Ventures + Lexington Partners, $6M purchase
IHG Brand Agreement Signed
Oct 2025
Holiday Inn Express & Suites flag confirmed
CRDA Loan Application
Nov 2025
$4M low-cost loan, regional committee approved
Technology Consultant Engaged ⚑
Feb 2026
HotelTechCon engaged for IT design & vendor management
IT Design & RFP Phase
Feb–Mar 2026
Low-voltage design, vendor RFPs, IHG compliance review
Vendor Contracts Signed
Mar 2026
All technology vendors under contract
Construction Start
Apr 2026
4-month renovation timeline
Technology Installation
May–Jul 2026
Phased install: infrastructure β†’ systems β†’ testing
Testing & Commissioning
Jul 2026
System testing, punch list, IHG certification
Grand Opening
Aug 2026
Holiday Inn Express & Suites β€” Hartford

🀝 Vendor Tracker

CategoryVendorStatusContract
PMSOracle OPERA Cloud (IHG mandate)Confirmed$45K
WiFi / HSIAIHG Connect (Nomadix/Ruckus)RFP Out~$85K
IPTVEnseo (IHG preferred)Evaluating~$110K
Door LocksDormakaba/ASSA ABLOYRFP Out~$95K
VoIP / PBXMitelNot StartedTBD
Low Voltage3 bids requested⚠️ Behind~$180K
Security/CCTVAvigilonNot StartedTBD
Digital SignageFour Winds InteractiveNot Started~$25K
BMS/EnergyHoneywellNot StartedTBD
POS (F&B)Infrasys (IHG approved)Confirmed$18K
Network InfraCisco MerakiEvaluating~$65K
Guest AppIHG One Rewards (mandated)StandardIncluded

πŸ’° IT Budget Tracker

PMS & Software
$63,000
HSIA / WiFi
$85,000
IPTV / In-Room Entertainment
$110,000
Door Locks
$95,000
Low Voltage / Cabling
$180,000
Network Infrastructure
$65,000
Security / CCTV
$75,000
Other (signage, BMS, VoIP)
$127,000

TOTAL IT BUDGET
$800,000
Committed
$126,000 (16%)
In RFP
$355,000 (44%)
Not Started
$319,000 (40%)

⚑ Action Items & Punch List

πŸ”΄ Needs Immediate Attention
!
Low-voltage RFP overdue β€” 3 bids requested 2 weeks ago, only 1 received. Follow up with remaining contractors TODAY.
!
IHG PIP compliance review β€” technology section of Property Improvement Plan not yet submitted to brand. Due Mar 1.
!
Suite technology spec undefined β€” 16 new suites need different tech spec than standard rooms (larger TV, additional outlets, workspace connectivity). Design not started.
🟑 In Progress
β†’
WiFi RFP evaluation β€” 2 proposals received, comparing coverage plans
β†’
IPTV vendor demo scheduled β€” Enseo demo Feb 28
β†’
Door lock spec β€” reviewing Dormakaba vs ASSA ABLOY for IHG mobile key compatibility
β†’
Network design β€” Meraki proposal under review, need to confirm switch count for 105 rooms + BOH
βœ… Completed
βœ“
Oracle OPERA Cloud PMS contract signed
βœ“
Infrasys POS selected and contracted
βœ“
Initial site survey completed β€” existing infrastructure assessed
βœ“
IHG technology standards document obtained and reviewed
βœ“
IT budget approved by ownership group