105
Rooms
$13.6M
Total Budget
$1.2M
IT Budget (est.)
12
Vendors Tracked
4
Months to Opening
3
Items Need Attention
π Project Timeline
Property Acquired
Aug 2025
DVR Ventures + Lexington Partners, $6M purchase
IHG Brand Agreement Signed
Oct 2025
Holiday Inn Express & Suites flag confirmed
CRDA Loan Application
Nov 2025
$4M low-cost loan, regional committee approved
Technology Consultant Engaged β‘
Feb 2026
HotelTechCon engaged for IT design & vendor management
IT Design & RFP Phase
FebβMar 2026
Low-voltage design, vendor RFPs, IHG compliance review
Vendor Contracts Signed
Mar 2026
All technology vendors under contract
Construction Start
Apr 2026
4-month renovation timeline
Technology Installation
MayβJul 2026
Phased install: infrastructure β systems β testing
Testing & Commissioning
Jul 2026
System testing, punch list, IHG certification
Grand Opening
Aug 2026
Holiday Inn Express & Suites β Hartford
π€ Vendor Tracker
| Category | Vendor | Status | Contract |
|---|---|---|---|
| PMS | Oracle OPERA Cloud (IHG mandate) | Confirmed | $45K |
| WiFi / HSIA | IHG Connect (Nomadix/Ruckus) | RFP Out | ~$85K |
| IPTV | Enseo (IHG preferred) | Evaluating | ~$110K |
| Door Locks | Dormakaba/ASSA ABLOY | RFP Out | ~$95K |
| VoIP / PBX | Mitel | Not Started | TBD |
| Low Voltage | 3 bids requested | β οΈ Behind | ~$180K |
| Security/CCTV | Avigilon | Not Started | TBD |
| Digital Signage | Four Winds Interactive | Not Started | ~$25K |
| BMS/Energy | Honeywell | Not Started | TBD |
| POS (F&B) | Infrasys (IHG approved) | Confirmed | $18K |
| Network Infra | Cisco Meraki | Evaluating | ~$65K |
| Guest App | IHG One Rewards (mandated) | Standard | Included |
π° IT Budget Tracker
PMS & Software
$63,000
HSIA / WiFi
$85,000
IPTV / In-Room Entertainment
$110,000
Door Locks
$95,000
Low Voltage / Cabling
$180,000
Network Infrastructure
$65,000
Security / CCTV
$75,000
Other (signage, BMS, VoIP)
$127,000
TOTAL IT BUDGET
$800,000
Committed
$126,000 (16%)
In RFP
$355,000 (44%)
Not Started
$319,000 (40%)
β‘ Action Items & Punch List
π΄ Needs Immediate Attention
!
Low-voltage RFP overdue β 3 bids requested 2 weeks ago, only 1 received. Follow up with remaining contractors TODAY.
!
IHG PIP compliance review β technology section of Property Improvement Plan not yet submitted to brand. Due Mar 1.
!
Suite technology spec undefined β 16 new suites need different tech spec than standard rooms (larger TV, additional outlets, workspace connectivity). Design not started.
π‘ In Progress
β
WiFi RFP evaluation β 2 proposals received, comparing coverage plans
β
IPTV vendor demo scheduled β Enseo demo Feb 28
β
Door lock spec β reviewing Dormakaba vs ASSA ABLOY for IHG mobile key compatibility
β
Network design β Meraki proposal under review, need to confirm switch count for 105 rooms + BOH
β
Completed
β
Oracle OPERA Cloud PMS contract signed
β
Infrasys POS selected and contracted
β
Initial site survey completed β existing infrastructure assessed
β
IHG technology standards document obtained and reviewed
β
IT budget approved by ownership group